Dale Street Reconstruction Workforce Report

Contact us

Ramsey County and the Minnesota Department of Transportation (MnDOT) track workforce hours and contracting on the Dale Street project. Figures will be updated on a monthly basis at this site.

Ramsey County Public Works is leading the project; Redstone Construction is serving as the primary contractor. 

Project goals and progress to date

Through June 2020

View the full July 2020 report (PDF)

Total project completion

  • Budget paid (certified work) as of July 7: $4,727,069.98 of $11,790,010.45 (40.1%)

Disadvantaged business enterprise (DBE)

Read about DBE on the MnDOT website

  • Federal and county goal: 9.5%
  • Redstone Construction project commitment: 10.2%, or $1,208,323.57
  • Certified work paid to date (July 7): $259,954.91 of $4,727,069.98 (5.5%)

Workforce goals

  • County goal for all construction projects: 32% people of color and 20% women
  • Federal goal: 2.9% people of color and 6.9% women
  • Redstone Construction workforce plan: 11.5% people of color and 5% women
  • Project hours to date (July 7): 12.2% people of color and 4.5% women

On-the-job training

  • Federal requirement: five trainees and 2,000 hours
  • To date (July 7): four trainees have worked 819.5 total hours

 