Mounds View Boulevard Improvements

Contact us

Mounds View Boulevard between Woodale Drive and and Silver Lake Road will be under construction starting in the fall of 2024 and continuing into 2025.

We will be replacing and updating four traffic signals and installing ADA accessible pedestrian ramps. This project also includes the replacement of some minor drainage infrastructure. 

Selected Contractor: Forest Lake Contracting, Inc.

Goals

  • Replace and update aging traffic signals.
  • Improve pedestrian safety by upgrading the existing sidewalk to meet current ADA guidelines.

Timeline​

May 

  • Woodale Drive is scheduled to be open May 23, weather dependent. 
  • Traffic Signal and stormwater work at County Road I continues through mid-June. 
  • Traffic Signal installation and utility work will begin the week of May 19, at County Road H2.  

June

  • Traffic signal work at County Road I will finish.  
  • Traffic Signal installation work will continue at County Rd H2.  

Traffic Impacts

  • County Road I is closed on the west side of Mounds View Boulevard; use posted detours on Silver Lake Road. 
  • County H2 closure on the east side is scheduled to begin the week of May 19. 
  • County Road H2 detour route is Quincy Street to County Road I. 
  • Northbound and southbound Mounds View Boulevard is reduced to one lane in the work zone. 