Hamline Avenue at Clarmar Avenue Drainage Project

Contact us

Ramsey County and the city of Roseville are partnering on a drainage project on Hamline Avenue at Clarmar Avenue. This project will reconstruct storm sewer pipe outletting to Lake Josephine to accommodate stormwater flows and alleviate surface flooding.

Project Contractor: Forest Lake Contracting

Timeline

  • September 
    • Week of September 29, work begins. 
    • Clear and remove brush and trees in the pipe easement. 
  • October 
    • Install watermain and stormsewer across Clarmar Avenue and Hamline Avenue. 
    • Install curb and gutter. 
    • Install fence and retaining wall. 
  • November
    • Restore and plant in the work zone. 
    • Complete road surface repair. 

Traffic Impacts

  • Expect traffic delays in the construction. Please follow posted signs and use alternative routes when possible. 

Project Area

Hamline and Clarmar project area map