Ramsey County and the city of Roseville are partnering on a drainage project on Hamline Avenue at Clarmar Avenue. This project will reconstruct storm sewer pipe outletting to Lake Josephine to accommodate stormwater flows and alleviate surface flooding.
Project Contractor: Forest Lake Contracting
Timeline
- September
- Week of September 29, work begins.
- Clear and remove brush and trees in the pipe easement.
- October
- Install watermain and stormsewer across Clarmar Avenue and Hamline Avenue.
- Install curb and gutter.
- Install fence and retaining wall.
- November
- Restore and plant in the work zone.
- Complete road surface repair.
Traffic Impacts
- Expect traffic delays in the construction. Please follow posted signs and use alternative routes when possible.